Tuesday, October 28, 2008

Sustainable energy update

We've made great progress on our renewable energy site - including running all of the electrical "chases" and pouring 15 tons of concrete for the pad including the base for the wind turbine tower and piers for the photovoltaic arrays. Now the concrete has to "cure" for thirty days before the tower can be erected. So far we're right on schedule for going live in January!

-Howard